SYDNEY (Centre for Asia Pacific Aviation) - Incheon International Airport announced the completion of 25% of Phase II KRW4.6 trillion expansion project at the airport. The project is expected to be completed by Jul-08, five months ahead of schedule. Construction works includes:

  • New 4,000m runway;
  • 120 hectare apron;
  • 16.5 hectare concourse; 13 hectare cargo terminal area.