19-Jun-2013 2:13 PM
Kuala Lumpur Airport terminal two to be operational in May-2014
Malaysia Airports Holdings announced (18-Jun-2013) contractors UEMC and Bina Puri confirmed a revised completion date of 30-Apr-2014 for the Kuala Lumpur International Airport terminal two (KLIA2) project. Malaysia Airports Holdings is targeting 02-May-2014 for the commencement of operations at the new facility. As previously reported by CAPA, the terminal was scheduled to be complete on 28-Jun-2013 and Malaysia Airports Holdings attributed the delay to insufficient resources. [more - original PR]